Korala Border Crossing Collects Rs 12 Billion in Four Months, but Infrastructure Development Stalls

Dragon Media Correspondent

Nearly four years after preparations began for a detailed project report (DPR), construction of integrated infrastructure at the Korala border crossing in Mustang, a strategically important alternative trade route between Nepal and China, has yet to commence. Despite substantial growth in trade and revenue collection, inadequate infrastructure continues to hamper border operations.

In February–March 2023, the government initiated a detailed project study for the construction of customs and immigration offices, quarantine facilities, a dry port and an integrated security post. Sitara Intucept–Fulbright JV completed the study, including geological assessments and soil testing, at a cost of Rs 10 million and submitted the report to the government.

The Korala crossing generated more than Rs 6 billion in revenue during the previous fiscal year. Revenue collection has already exceeded Rs 12 billion in the first four months of the current fiscal year. Between 60 and 70 freight containers and approximately 100 electric vehicles are entering Nepal through the crossing daily.

The closure of the Tatopani and Rasuwagadhi border crossings has further increased trade traffic through Korala. Without a dry port, adequate parking facilities or charging stations, freight containers are being parked along roadsides, while electric vehicles are being kept in unsafe areas near riverbanks and steep slopes.

Lopsang Chhompel Bista, Chairman of Loghekar Damodarkunda Rural Municipality, has urged the government to expedite infrastructure development to transform Korala into a well-managed international trade and transit hub.

A total of 1,436 ropanis of land has been allocated to various government agencies in the Korala area. Although separate plots have been designated for customs, immigration and security agencies in Nhechung, permanent customs and immigration office buildings have yet to be constructed. The Armed Police Force, however, has completed its building.

During a recent inspection by the Infrastructure Development Committee of the House of Representatives, local representatives called for infrastructure investment alongside revenue collection and prioritised upgrading the Beni–Jomsom–Korala road.

Given Korala’s growing importance for Nepal–China trade, transit diversification and the economic development of Gandaki Province, pressure is mounting on the government to develop infrastructure commensurate with the crossing’s expanding commercial potential.